Key TakeawaysIntel said it plans to push back the opening of two chipmaking facilities currently under construction in ...
Intel’s plans to build two chip factories in New Albany, Ohio for an investment of more than $28 billion have been postponed.
Intel is delaying the opening of its Ohio chip manufacturing facility, the embattled chipmaker said Friday. Intel said it won ...
Intel’s massive computer chip factory, originally scheduled to open this year, has been delayed again, this time to the next ...
Thanks to the bipartisan CHIPS Act, tech giant Intel chose to invest billions in Ohio to develop a massive semiconductor ...
Concerns about Intel's long-awaited multi-billion dollar manufacturing plant in Ohio continue to swell as the tech giant has ...
Intel originally said it expected to begin production at the New Albany, Ohio, site in 2025, and later pushed that back to ...
The interim leaders "brought the discipline and focus needed to improve our execution, stabilize our performance and position our company for the future," Intel Chairman Frank Yeary said in a public ...
The first phase of the facility, known as Mod 1, should be finished in 2030, with chip production beginning between 2030 and ...
There is still hope the project will happen as Intel promises, but if the plan falls through, the state must claw back as much as possible.
Intel's first Ohio chip fabrication plant may not open until 2030 at the earliest, according to a report in The Columbus ...
Intel's promised $28 billion chip fabrication plants in Ohio are facing further delays, with the first factory in New Albany ...